| Citation(s) |
|---|
| 2001 SLG 3450 = 2001 SLD 3450 = 2001 MLD 1879 |
Court of Special Judge, Karachi
Suit No. 897 of 1980, decided on 24th November, 1999.
Presented By: Sabihuddin Ahmed, J
Ali Akbar for Plaintiffs. Ismail Merchant for Defendants.
Suit No. 897 of 1980, decided on 24th November, 1999.
Presented By: Sabihuddin Ahmed, J
Ali Akbar for Plaintiffs. Ismail Merchant for Defendants.
SADDARUDDIN and others‑‑‑Plaintiffs
VERSUS
Messrs NATIONAL CONSTRUCTION CO. (PAK.) LTD. and others‑‑‑Defendants
Law: Sale of Goods Act (III of 1930)
Section: 57
Sales of Goods Act (III of 1930) S. 57‑‑‑Suit for damages for non‑delivery of goods‑‑‑Defendants/sellers of goods despite receiving total price of goods in advance made past delivery of goods to the plaintiff/buyers, and failed to deliver remaining goods in time as provided in the terms and conditions of contract of sale‑‑‑Defendants sold undelivered quantity of goods at the risk of the plaintiff/buyers‑‑‑No evidence had been produced by the defendants/sellers to show that such risk sale was effected after notice to the plaintiffs and even particulars thereof had not been furnished by the defendants‑‑‑Risk sale being unjustified, the suit filed by plaintiff was decreed accordingly. Date of hearing: 27th October, 1999. JUDGMENT Through this suit for recovery of money the plaintiffs have claimed Rs.1,203,300 by way of refund of money and damages for breach of contract on the part of the defendants. According to the plaint the defendant invited public offer for the sale of 20 pontoons available with them on as is where is basis and the plaintiffs, who are dealers in iron and general scraps made an offer of Rs.4,150 per metric ton. The plaintiff's offer was accepted by the defendants on 3‑4‑1980 with slight modification. The plaintiffs advanced a total sum of Rs.325,000 to the defendants on different dates in April, 1980. However, while only four pontoons were delivered to the plaintiff, some difficulties were experienced in giving effect and after some correspondence the agreement was modified in terms of the defendants' letter dated 5‑5‑1980 addressed to the plaintiffs. The salient feature whereof appeared to be as (i) The remaining pontoons would be delivered to the plaintiff No. 1. "Timber Point Site" within 45…