| Citation(s) |
|---|
| 2001 SLG 3421 = 2001 SLD 3421 = 2001 MLD 1804 |
Peshawar High Court
Writ Petition No. 37 of 1994, decided on 15th March, 2001
Presented By: Talaat Qayyum Qureshi and Malik Hamid Saeed, JJ
Muhammad Sardar Khan for Appellant. Jehanzab Rahim for
Respondent.
Writ Petition No. 37 of 1994, decided on 15th March, 2001
Presented By: Talaat Qayyum Qureshi and Malik Hamid Saeed, JJ
Muhammad Sardar Khan for Appellant. Jehanzab Rahim for
Respondent.
Chaudhry ABDUL RAUF MITHU‑‑‑Petitioner
VERSUS
CHAIRMAN, SARHAD DEVELOPMENT AUTHORITY, PESHAWAR and 4 others‑‑‑Respondents
Law: Constitution of Pakistan, 1973
Section: 199, 25
(a) Constitution of Pakistan (1973) Art. 199‑‑‑Constitutional petition‑‑‑Allotment of plot ‑‑‑Interest‑‑‑Non- payment of price of such plot to the Authorities within stipulated time‑‑ Interest, charge of‑‑‑Authorities included certain amount of interest in the price of the plot as the payment was not made in the due course of time‑‑ Validity‑‑‑High Court declined to allow the payment of interest as the same had been declared to be un‑Islamic by the Supreme Court. (b) Constitution of Pakistan (1973) Art. 199‑‑‑Constitutional petition ‑‑‑Pendency of petition ‑‑‑Interest‑‑ Petitioner failed to make the payment of plot allotted to him within stipulated period‑‑‑Authorities alongwith the original price included certain amount of interest for the period during, which the petition was pending before High Court‑‑‑Validity‑‑‑Petitioner could not be penalized for the period for which his petition was pending for decision. (c) Constitution of Pakistan (1973) Art. 199‑‑‑Constitutional petition‑‑‑Contractual obligation‑‑ Maintainability‑‑‑ Cancellation of allotment of plot by the Authority to the petitioner‑‑‑Contention of Authorities was that since petitioner intended to enforce contractual obligation, petition was not maintainable ‑‑‑Validity‑‑ Petitioner had challenged the validity of cancellation letter whereby plot allotted to him was cancelled‑‑‑Where the cancellation by the Authorities pertained to the performance of statutory obligation and functions of the Authorities, the act of the Authorities was susceptible to exercise of Constitutional jurisdiction of High Court‑‑‑When State functionary entered into a contract with a private citizen/limited company, any serious contravention of Rules or instructions would be amenable to Constitutional jurisdiction of High Court‑‑‑Matter before the Court in the present case simply pertained to the cancellation of allotment of plot and petitioner did not want to enforce contractual obligation‑‑‑Petition was maintainable in circumstances. Pakistan Medical Association, Karachi v. Government of Sindh and 5 others 1979 CLC 382; Haji Noor Muhammad and another v. K.D.A. and others PLD 1975 Kar. 373 and Rashid A. Khan v. West Pakistan…