| Citation(s) |
|---|
| 2026 SLG 5390 = 2026 SLD 5390 = 2026 CLC 1656 |
Peshawar High Court
Writ Petition No. 5526-P of 2018, decided on 25th February, 2026.
Presented By: Syed Arshad Ali and Ms. Farah Jamshed, JJ
Waqar Orakzai, Farhan Qadeer, A.A.Gs. and Asad Jan along with Ihsanullah, Electric Inspector, Asif Jamal, Assistant Electric Inspector and Ms. Mehnaz (Law Officer) on behalf of Energy and Power Department for
Respondents.
Writ Petition No. 5526-P of 2018, decided on 25th February, 2026.
Presented By: Syed Arshad Ali and Ms. Farah Jamshed, JJ
Waqar Orakzai, Farhan Qadeer, A.A.Gs. and Asad Jan along with Ihsanullah, Electric Inspector, Asif Jamal, Assistant Electric Inspector and Ms. Mehnaz (Law Officer) on behalf of Energy and Power Department for
Respondents.
SAIF TEXTILE MILLS LIMITD and others ---Petitioners
VERSUS
GOVERNMENT OF KHYBER PAKHTUNKHWA through Chief Secretary, Peshawar and 2 others ---Respondents
Law: Electricity Act (IX of 1910)
Section: 26
Law: Finance Act, 1964
Section: 13
Electricity Act (IX of 1910) S. 26---West Pakistan Finance Act (XXXI of 1964), S. 13---Khyber Pakhtunkhwa Finance Act (XII of 2007), Fifth Schedule---Supply of electricity---Electricity duty, imposition of---Provincial jurisdiction---Self-generation---Supply of electricity to own units---Line transformation and transmission losses---Petitioners/companies were aggrieved by electricity duty payable by them with respect to line transformation and transmission losses and electricity supplied to their own units---Held: Scope and function of a licensee were triggered only at the recovery stage, and that too in respect of general electricity duty charged under S. 13(1) of the West Pakistan Finance Act, 1964---Demand in question was raised against the petitioners/companies in respect of electricity self-generated by them; therefore, essential to the controversy was S. 13(4) of the West Pakistan Finance Act, 1964, which provided that in the case of energy other than that supplied by a licensee, the person generating the energy shall pay to the Government the electricity duty payable under this section in respect of the energy consumed, in such manner as may be prescribed ---Prior to the amendment in the Fifth Schedule through the Khyber Pakhtunkhwa Finance Act, 2007, a reading of S. 13(4) of the West Pakistan Finance Act, 1964 contemplated a scenario where energy was generated by a person who was not a licensee but was nonetheless supplying energy to a consumer---Notwithstanding the constitutional scheme relating to the authority of the Province to levy electricity duty, a plain reading of S.13(4) of the West Pakistan Finance Act, 1964 read with Entry No. (e) of the Fifth Schedule to the Khyber Pakhtunkhwa Finance Act, 2007 confirmed the validity of electricity duty imposed by the Province---High Court declined to interfere with the demand raised by the authorities---Constitutional petition was dismissed, in circumstances. M.Y. Electronic Industries (Pvt) Ltd. v. Government of Pakistan 1998 SCMR 1404; Government of Punjab through Secretary Irrigation and Power and another v. Kunjah Textile Mills Ltd. and others 2025 SCMR 239 and The…