Quetta High Court
C.M.A. No. 11 of 2022
Presented By: Muhammad Ejaz Swati and Sardar Ahmed Haleemi, JJ.
Mr. Shahid Baloch, Additional A.G for Appellant. M/s. Rehmatullah Barrech and Ahsanullah Kakar, Advocates for
Respondents. Date of hearing: 3.10.2022.
C.M.A. No. 11 of 2022
Presented By: Muhammad Ejaz Swati and Sardar Ahmed Haleemi, JJ.
Mr. Shahid Baloch, Additional A.G for Appellant. M/s. Rehmatullah Barrech and Ahsanullah Kakar, Advocates for
Respondents. Date of hearing: 3.10.2022.
SECRETARY COMMUNICATION AND WORKS, GOVERNMENT OF BALOCHISTAN, QUETTA and others—Appellant
VERSUS
MIRWAIS KHAN and another--Respondents
Law: Land Acquisition Act, 1894
Section: 18
Land Acquisition Act, 1894 (I of 1894)-- ----S. 18--Construction of fly-over--Acquisition of land--Bifurcation of land--Reference filed--Assessment of price--Reference allowed--order of trial Court was challenged--Referenced dismissed--Time-barred--Direction to--Opportunity of producing evidence--Appeal--Delay of five months--The impugned judgment and decree was challenged after delay of five (05) months which had not been explained--Initially Law and Parliamentary Office’s vide letter addressed to AG Balochistan requested for filing appeal against impugned judgment, which was duly replied to Appellant No. 2 that no plausible reason had been provided for delay caused in filing appeal, further appellant No. 2 was directed to explain reason of delay caused and also initiate enquiry against concerned officials who sent appeals to AG Office after lapse of stipulated period--The query of AG Balochistan was not replied with, appeal was not filed through AG Office--It is settled principle of law that where an appeal is not filed within stipulated period creates valuable rights in favour of opposite party, such valuable rights cannot be taken away unless very strong, convincing and solid Grounds are shown for condoning delay--In absence of any valid explanation of delay for each and every day, mere assertion that appellants were unable to accord necessary sanctions timely from law department was not sufficient to condone delay of 5 months and 6 days, as such, instant appeal was not maintainable--Appeal dismissed. [Para 9 & 10] A, B & C Mr. Shahid Baloch, Additional A.G for Appellant. M/s. Rehmatullah Barrech and Ahsanullah Kakar, Advocates for Respondents. Date of hearing: 3.10.2022. Judgment Sardar Ahmad Haleemi, J.--This appeal…