| Citation(s) |
|---|
| 2025 SLG 5210 = 2025 SLD 5210 = 2025 PLJ 55 |
Sindh High Court
Const. P. Nos. D-650, D-676 of 2024
Presented By: Adnan-ul-Karim Memon and Amjad Ali Bohio, JJ.
Mr. Kanji Mal, Advocate for Petitioners (in C.P No. 650/2024). Mr. Mir Parvez Talpur, Advocate for Petitioner (in C.P. No. 676/2024). Mr. Nisar Abro, D.A.G, Pakistan. Mr. Sharif Solangi. A.A.G Sindh. Date of hearing: 12.8.2024.
Const. P. Nos. D-650, D-676 of 2024
Presented By: Adnan-ul-Karim Memon and Amjad Ali Bohio, JJ.
Mr. Kanji Mal, Advocate for Petitioners (in C.P No. 650/2024). Mr. Mir Parvez Talpur, Advocate for Petitioner (in C.P. No. 676/2024). Mr. Nisar Abro, D.A.G, Pakistan. Mr. Sharif Solangi. A.A.G Sindh. Date of hearing: 12.8.2024.
ABDUL NASIR KHAN and others--Petitioners
VERSUS
FEDERATION OF PAKISTAN through Secretary PDSI and others--Respondents
Law: Constitution of Pakistan, 1973
Section: 4, 9, 199
Constitution of Pakistan, 1973-- ----Arts. 4, 9 & 199--Establishment of sub-campus--Timeline--Significant delay--Interim campus--Approval of university project--16% completion of project--Exceeding of project timeline--Irregularities in procurement process--Infringement of fundamental rights--Jurisdiction--Impugned action on part of Respondents No. 03 to 07 could infringe on fundamental rights of students to get quality education as guaranteed under Constitution, which raises serious questions of public importance, relating to rights of students of Mirpurkhas--High Court can examine exercise of discretion of competent authority of respondents--HEC would continue to check overall will of respondent-university to setup Sukkur IBA University Mirpurkhas Campus--HEC would help out in setting up IBA University, Mirpurkhas Campus--Petitions disposed of. [Para 7 & 8] A, B & C Mr. Kanji Mal, Advocate for Petitioners (in C.P No. 650/2024). Mr. Mir Parvez Talpur, Advocate for Petitioner (in C.P. No. 676/2024). Mr. Nisar Abro, D.A.G, Pakistan. Mr. Sharif Solangi. A.A.G Sindh. Date of hearing: 12.8.2024. Order Adnan-ul-Karim Memon, J.--Petitioners are seeking the following relief(s):- a. That this Honorable Court may be pleased to direct the Respondents No. 01, and 05 to remove the cap from the Sukkur IBA University Mirpurkhas Campus and release the development funds to re-start the construction of the subject University Campus under the administrative approval and PC-1 of the project. b. That this Honorable Court may be pleased to direct Respondents No. 06 and 07 to not nonfunctional the Sukkur IBA University Mirpurkhas Campus. c. That this Honorable Court may be pleased to direct the Respondent No. 06 and 07 to include the Sukkur IBA University Mirpurkhas Campus in the Crash Preparatory Classes-2024, starting from May 13, 2024 d. That this Honorable Court may be pleased to suspend the…