| Citation(s) |
|---|
| 2025 SLG 5184 = 2025 SLD 5184 = 2025 PLJ 109 |
Islamabad High Court
F.A.O. No. 108 of 2019
Presented By: Miangul Hassan Aurangzeb And Mr. Saman Rafat Imtiaz, JJ.
Barrister Farrukh Jawad Panni, for Appellant (in F.A.O. No. 108/2019) and for
Respondent No. 1 (in C.R. No. 136/2019). Mr. Saeed Ahmed Zaidi, Advocate for
Respondents No. 1 and 2 (in F.A.O. No. 108/2019) and for Petitioners (in C.R. No. 136/2019). Date of hearing: 29.1.2025.
F.A.O. No. 108 of 2019
Presented By: Miangul Hassan Aurangzeb And Mr. Saman Rafat Imtiaz, JJ.
Barrister Farrukh Jawad Panni, for Appellant (in F.A.O. No. 108/2019) and for
Respondent No. 1 (in C.R. No. 136/2019). Mr. Saeed Ahmed Zaidi, Advocate for
Respondents No. 1 and 2 (in F.A.O. No. 108/2019) and for Petitioners (in C.R. No. 136/2019). Date of hearing: 29.1.2025.
PEB STEEL ALLIANCE LIMITED--Appellant
VERSUS
EARTHQUAKE RECONSTRUCTION & REHABILITATION AUTHORITY and others--Respondents
Law: Code Of Civil Procedure, 1908.
Section: O.VII R. 11
Law: Arbitration Act, 1940
Section: 34 , 39(1)(v)
Civil Procedure Code, 1908 (V of 1908)-- ----O.VII R. 11--Arbitration of Act, 1940 (IX of 1940), Ss. 34 & 39(1)(v)--Proceedings in suit were stayed--Application for rejection of plaint was dismissed--Award of contract--Joint venture agreement--Submission of bid--Bid was accepted--Claim for reimbursement of income tax--Payment of amount into JV’s bank account which was not operated by appellant--Arbitration clause--Execution of contract--Challenge to--PERRA, instead of paying an amount equivalent to US Dollars 423,469 directly to PEB paid same into a bank account which was operated by A&ACC and Buildcore who were PEB’s partners--Civil Court erred by staying proceedings in suit also against PERRA on basis of arbitration clause in JV Agreement to which PERRA was not even a party--Discretion in refusing to stay legal proceedings should be exercised by Court in a sparing and cautious manner as a prima facie duty is cast upon Courts to act upon agreement--PEB’s dispute with PERRA for not paying an amount equivalent to US Dollars 423,469 against IPC No. 84 directly to PEB through L/C was inextricably intertwined with dispute that PEB had with its JV partners as latter did not remit PEB’s share in amount deposited by PERRA in JV’s bank account which PEB could not operate--PEB could not be asked to prosecute its remedy against ERRA and PERRA separately from A&ACC and Buildcore otherwise there might be a possibility of conflicting decisions by two different fora--That was sufficient reason for A&ACC and Buildcore’s application under Section 34 of 1940 Act to be dismissed--Granting of stay would result in allowing case of plaintiff against some of defendants to be determined by arbitration, leaving case against rest of defendants to be decided by Court--Civil Court did not commit any jurisdictional irregularity by dismissing said application under Order VII, Rule 11 CPC--Appeal allowed. [Pp. 113, 114, 115, 116, 120, 123, 124,…