2014 SLG 595 2014 SLD 595 2014 MLD 1253
Lahore High Court
Writ Petition No. 14493 of 2012, decided on 16-01-2014.
SHOAIB SAEED, JUSTICE
Malik Kashif Rafiq Rajwana for Petitioner. Rao Muhammad Iqbal for
Respondents.

MESSRS MEHMOOD TEXTILE MILLS LTD. THROUGH GENERAL MANAGER FINANCE

VS

MULTAN ELECTRIC POWER COMPANY (MEPCO) THROUGH

Law:

Section:

Constitution of Pakistan--- ----Art.199---Constitutional petition---Electrical power company---Overdue payment---Stoppage of payment due to audit objection---Scope---Petitioner/electric supply company supplier under agreement with Multan Electric Power Company (MEPCO), had supplied electricity but the amount/payment due on account of supply of electricity was not released---MEPCO informed the petitioner/electric supplier that its payments were withheld on account of audit objections---Contention of the petitioner/electric supplier was that audit objection was internal affair of MEPCO and payment could not be denied on this ground---Validity---In view of Revised Power Generation Agreement, MEPCO was bound to make payments against invoices, submitted for the relevant months---Respondent/MEPCO had admitted that payments were withheld due to audit objection, which was a matter between MEPCO and its audit department---MEPCO was directed by High Court to release the long overdue withheld payment of petitioner/ electric supplier along with prescribed mark-up---Constitutional petition was accepted. WAPDA through Chairman and 3 others v. Fazal Karim and 5 others 2008 YLR 308 and Water and Power Development Authority and others v. Umaid Khan 1988 CLC 501 ref. THIS ORDER PASSED BY: SHOAIB SAEED, J.--- Petitioner is a holder of Generation Licence issued by National Electric and Power Regulatory Authority (hereinafter referred as "NEPRA") for its own power generation. In this regard on 6-10-2001 petitioner company entered into an agreement for supply of electricity of MEPCO (respondent) where-under the company offered to sell/supply 5-MW of power to MEPCO (respondent) which was accepted resulting into a Power Purchase Agreement (hereinafter referred as PPA) dated 4-6-2007. The PPA executed between the parties was for a period of one year till June 2008. On its expiry a Revised Power Generation Agreement (hereinafter referred as RPPA) dated 28-2-2009 was executed between the parties for a period of five years and under fresh terms supply of 9-MW of Power was to be supplied till its expiry in February, 2014. Electricity was supplied by petitioner company to MEPCO (respondent)…
🔒
Continue readingLogin or create an account to access the complete content.Login / Register

Deprecated: trim(): Passing null to parameter #1 ($string) of type string is deprecated in /home/digixyei/sldsystempk.com/view/master-layout/view_case.php on line 492